EXCAVATION MAN HOUR

Below are the list of excavation man hour either using an excavator or manual labor only. Man hours are listed are either per 100 cubic meter or per cubic meter.

For othe reference price list, kindly check the item below:
– Formwoks price list, please check the link: FORMWORK PRICE LIST
– Scaffolding price list, please check the link: SCAFFOLDING PRICE LIST
– Reinforced concrete pipe price list, please check the link: RCP PRICE LIST
– Ready mix concete price list, please check the link: RMC PRICE LIST

EXCAVATION MAN HOUR – USING AN EXCAVATOR

Note: Operation hours/Manhours includes excavation and loading onto truck/hauler. 

Soil TypeExcavator Bucket SizeOperation Hours per 100m3 of excavation
ExcavatorOperatorMechanicLaborer
Light0.75 m3 Bucket1.841.841.841.84
0.5 m3 Bucket1.971.971.971.97
0.3 m3 Bucket2.622.622.622.62
Medium0.75 m3 Bucket3.413.413.413.41
0.5 m3 Bucket4.984.984.984.98
0.3 m3 Bucket5.765.765.765.76
Heavy0.75 m3 Bucket4.584.584.584.58
0.5 m3 Bucket5.245.245.245.24
0.3 m3 Bucket6.416.416.416.41
Hard Pan0.75 m3 Bucket5.765.765.765.76
0.5 m3 Bucket6.026.026.026.02
0.3 m3 Bucket7.987.987.987.98
Rock0.75 m3 Bucket5.765.765.765.76
0.5 m3 Bucket6.026.026.026.02
0.3 m3 Bucket7.987.987.987.98

EXCAVATION MAN HOURS – MANUAL LABOR

Note: Man hours includes excavation and loading onto truck/hauler. 

Soil TypeSoil ConditionManhours per one (1) cubic meters of excavation
First Lift2nd LiftThird Lift
LightDry1.41.841.84
Wet2.11.971.97
MediumDry2.13.413.41
Wet2.84.984.98
HeavyDry3.54.584.58
Wet4.25.245.24
Hard PanDry4.95.765.76
Wet5.66.026.02

DISPOSAL OF HAULED MATERIALS

Note: Driver Manhours will be equal to the operation hour of the Truck / Dump Truck / Hauler

Manhours per 100 cubic meter of hauled materials
Truck CapacityDistance of HaulingAverage Speed 10 KPHAverage Speed 20 KPH
DumptruckTruck DriverMechanicDumptruckTruck DriverMechanic
2m31Km6.616.611.244.634.631.24
2Km9.69.61.246.176.171.24
3Km12.4212.421.337.627.621.33
4Km15.8615.861.339.259.251.33
5Km18.3718.371.1111.2311.231.11
3m31Km5.65.61.053.923.921.05
2Km8.038.031.055.165.161.05
3Km10.7110.7116.546.541.09
4Km13.0813.0817.737.731.09
5Km15.5115.510.659.179.170.75
4m31Km4.764.760.93.333.330.85
2Km6.876.870.94.394.390.9
3Km9.049.040.965.55.50.9
4Km11.111.11.066.566.560.9
5Km13.2213.220.97.837.830.85
6m31Km2.782.780.51.991.990.5
2Km4.074.070.52.582.580.5
3Km5.215.210.553.233.230.5
4Km6.546.540.553.773.770.5
5Km7.737.730.654.464.460.55

HELP US

We want to improve this website so we need your help. Please send us your recommendations, suggestion, and request. Click this for the Suggestion Form Page.

Dont forget to hit Like and Share if this blog helped you.

FOLLOW US!

Please like and follow our facebook page for social media updates.

https://www.facebook.com/theprojectestimate