CONSTRUCTION LABOR COST

Below is the average range of construction labor cost for site works. The data will serve as the basis of your estimate since every project is different from the other. Take note that the labor cost are rate per day in Philippine Peso.  

For other project estimation reference, please check the other items below:
– Construction equipment rental rates, please check the link: EQUIPMENT RENTAL COST
– Excavation man hours, please check the link: EXCAVATION MAN HOURS
– Materials for form works, please check the link: FORMWORK PRICE LIST
– Materials for scaffolding works, please check the link: SCAFFOLDING PRICE LIST
– Consumable materials, please check the link: COMMON AND CONSUMABLE MATERIALS PRICE

LABOR COST

RATE PER DAY

Philippines Construction Labor Rates
Item No.PositionManila Rate per dayProvincial Rate per day
Cost RangeCost Range
1Foreman650815520800
2Fitter530555450540
3Welder535550430535
4Electrician530560390510
5Carpenter535540400450
6Painter520550390440
7Mason512535380450
8Driver500540350450
9Eqpt Operator530550400450
10Helper512520280430

RATE PER HOUR

Philippines Construction Labor Rates
Item No.PositionManila Rate per HrProvincial Rate per Hr
Cost RangeCost Range
1Foreman81.25101.87565100
2Fitter66.2569.37556.2567.5
3Welder66.87568.7553.7566.875
4Electrician66.257048.7563.75
5Carpenter66.87567.55056.25
6Painter6568.7548.7555
7Mason6466.87547.556.25
8Driver62.567.543.7556.25
9Eqpt Operator66.2568.755056.25
10Helper64653553.75

Take note that salary of each personnel will be differ from each region, company, experience and scope of works. For example, let say that you will hire a electrician, an ordinary electrician with power and lighting experience will be compensated less compared to an industrial electrician with experience involved in medium/low voltage switchgears, motor control centers and automation. Of course, you will also evaluate the scope of work on what electrician’s experience you need for the job to be productive.

Factors regarding the productive rate will also need to be considered as what we have explained in BASIC LABOR ESTIMATION GUIDE in situation such as the business economy is excellent on that region or you will not hire local workers instead you will bring your own team to that region.

When it comes provincial rates, there are now provinces where construction are booming such as Iloilo City or Cebu City, so will expect that labor cost will be higher in this areas compared to other provinces. Projects must be evaluated and analyzed carefully before you start cost estimation.

HELP US

We want to improve this website so we need your help. Please send us your recommendations, suggestion, and request. Click this for the SUGGESTION FORM PAGE.

Dont forget to hit Like and Share if this blog helped you.

FOLLOW US!

Please like and follow our facebook page for social media updates.

https://www.facebook.com/theprojectestimate