Rebar Productivity Rate

The data written below for rebar productivity rate are the average output per hour of the task or activity. The described activity has a recommended list of teams for labor and equipment. Please take note that these are suggested values and for reference only. Each project has a different approach. Factors, wastage and allowances should be considered while doing estimates.

For other civil works productivity rates, please check below the list of items:
– Masonry works and installation man-hours, please see the link: MASONRY WORK PRODUCTIVITY RATE
– Concreting works and installation man-hours, please see the link: CONCRETE WORK PRODUCTIVITY RATE

For other material price list, please check below the list of items:
– Reinforced concrete pipe, please see the link: RCP PIPE PRICE LIST
– Ready mixed concrete, please see the link: RMC PRICE LIST
– Rebar steel price list, please see the link: REBAR PRICE LIST
– I beam price list, please see the link: I-BEAM PRICE LIST

REBAR PRODUCTIVITY RATE

REINFORCING BAR

ITEM NO. ACTIVITY / DESCRIPTION SIZE / DIMENSION UNIT TEAM COMPONENTS AVE. OUTPUT – HOURS / UNIT
LABOR EQUIPMENT UNIT
1 Beams & Girders 10 mm to 25 mm Metric Ton 0.25
4.00
2.00

0.25

1.00
0.125
0.125
Foreman
Steelman
Laborer / Helper
Equipment Operator
Power Tools
Crane Low Bed Truck
45.50 8.75 Hrs / Metric Ton
2Beams & Girders25 mm to 40 mmMetric Ton30.009.00Hrs / Metric Ton
3Columns10 mm to 25 mmMetric Ton42.0012.60Hrs / Metric Ton
4Columns25 mm to 40 mmMetric Ton35.0010.50Hrs / Metric Ton
5Spirals10 mm to 350mmMetric Ton35.0010.50Hrs / Metric Ton
6Elevated Slabs10 mm to 25 mmMetric Ton23.337.00Hrs / Metric Ton
7Footings10 mm to 25 mmMetric Ton30.009.00Hrs / Metric Ton
8Footings25 mm to 40 mmMetric Ton23.337.00Hrs / Metric Ton
9Slab on Grade10 mm to 25 mmMetric Ton26.257.88Hrs / Metric Ton
10Walls10 mm to 25 mmMetric Ton23.337.00Hrs / Metric Ton
11Walls25 mm to 40 mmMetric Ton19.095.73Hrs / Metric Ton
12Typical in Place10 MT (Ave.)Metric Ton38.1811.45Hrs / Metric Ton
13Typical in Place45 MT (Ave.)Metric Ton30.009.00Hrs / Metric Ton

HANDLING OF REBAR

ITEM NO. ACTIVITY / DESCRIPTION UNIT TEAM COMPONENTS AVE. OUTPUT – HOURS / UNIT
14 Unloading, handling, & sorting steel reinforcement Metric Ton 0.25
4.00
2.00
0.50

0.50
0.50
0.50
Foreman
Steelman
Laborer / Helper
Equipment Operator
Eqpt. Op. Oiler
Crane
Low Bed Truck
0.76 0.11 Hr / Metric Ton

STEEL DOWELS

ITEM NO. ACTIVITY / DESCRIPTION SIZE / DIMENSION UNIT TEAM COMPONENTS AVE. OUTPUT – HOURS / UNIT
15 Steel Dowels, 600mm Long 10 mm Piece 0.125
2.00
1.00
Foreman
Steelman
Laborer / Helper
0.07 0.00 Hr / Piece
16 Steel Dowels, 600mm Long 15 mm Piece 0.09 0.00 Hr / Piece
17 Dowels, Steel, 600mm Long 20 mm Piece 0.10 0.00 Hr / Piece
18 Steel Dowels, more than 600mm > 20mm Kilogram 0.09 0.00 Hr / Kilogram
19 Smooth dowels, 300mm long 10 mm Piece 0.26 0.00 Hr / Piece
20 Smooth dowels, 300mm long 16 mm Piece 0.31 0.00 Hr / Piece
21 Dowel caps, 125mm long 20 mm Piece 0.34 0.00 Hr / Piece
22 Dowel caps, 125mm long 32 mm Piece 0.04 0.00 Hr / Piece

SPLICING OF REBAR

ITEM NO. ACTIVITY / DESCRIPTION SIZE / DIMENSION UNIT TEAM COMPONENTS AVE. OUTPUT – HOURS / UNIT
23 Buttweld column bar splice 35 mm Piece 1.0
4.00
2.00

1.00
Foreman
Steelman
Laborer / Helper
Power Tools
0.84 0.24 Hr / Piece
24 Column splice clamp, sleeve/wedge 35 mm Piece 0.49 0.14 Hr / Piece
25 Mechanical splice sleeve type 35 mm Pc 1.07 0.31 Hr / Piece
26 Splicing Straight Rebar, mechanical threading 35 mm Piece 0.98 0.28 Hr / Piece
27 Splicing Straight Rebar, mechanical threading 40 mm Piece 1.31 0.37 Hr / Piece
28 Splicing Bent Rebar, mechanical threading 40 mm Pc 1.63 0.47 Hr / Piece

HELP US

We want to improve this website so we need your help. Please send us your recommendations, suggestion, and request. Click this for the SUGGESTION FORM PAGE.

Don’t forget to hit Like and Share if this blog helped you

FOLLOW US!

Please like and follow our Facebook page for social media updates.

facebook.com/theprojectestimate